(Admin note: Non Standard House member Doug has kindly put together the following excellent post showing the complete process of a cast iron flue removal inside a typical BISF house. In creating this post and taking the time to record the entire process, Doug hopes that he can share his experience with other members and more importantly he hopes that it may be a useful resource for others. Our sincere thanks to Doug for this valuable contribution)

Hello everyone here at BISF House.

I recently removed the cast iron flue and fireplace from a BISF house and thought that I would share it with you all. This post relates to BISF Houses where the fireplace is fitted to wall between the living & dining rooms.

Before starting there are few safety points to bear in mind.

  • You will need a 6-12 inch cast chain cutter. This is a heavy item and will require 2 persons to complete the job.
  • Always wear safety glasses and gloves and if possible, steel toecap shoes just in case.
  • Always wear a high quality dust mask and wherever possible always dampen down any insulation material that may surround the flue with a spray bottle of water. Although not prescribed, we can never rule out the possibility that installers may have used asbestos insulation in some cases. If you suspect the presence of asbestos do not undertake this work until the material has been correctly tested by an approved body.
  • Always wear a disposable work overall with hood as this can be an extremely dusty job.
  • Never use an angle grinder as sparks can easily ignite insulation or travel under floorboards, causing fire.
  • A strong working platform and extra lighting in the roof would also be a good idea.
  • Don't remove any of the supporting frames yet as it contains the pipe clamps which keeps the flue pipe in place. You can work around the frame without any problem.E
  • Ensure that any and all pipework leading into or out of the fireplace are disconnected or safely capped off away from the work area.
  • All gas pipes should be disconnected by a Corgi registered engineer.
  • Any electrical connections should be removed by a qualified electrician.
  • Water pipes if present should also be removed and capped if of no further use.
  • Always turn the gas off at the mains prior to undertaking any work as there may be hidden gas pipes that you are not aware of.

Originally, BISF houses were fitted with open coal fires that heated a small sealed back boiler that was situated behind the main firebox. This was a basic water or oil filled unit that heated radiators in the house. If still present, the box and pipework should be capped and carefully removed.

Admin Update: There have been a number of safety incidents including one fatality where old solid fuel back boilers have exploded due to the re-commisioning of old coal fires. Such events are not specific to BISF Houses. Please see http://www.hse.gov.uk/services/localgovernment/boilers.htm

In the 1980's many BISF properties were fitted with Baxi Bermuda gas fires with integrated backboiler. The back boiler was positioned inside the firebox, directly behind the fire itself.
This fire is fairly straightforward to remove once the gas feed has been safely disconnected. The front of the gas fire can pulled forward and carefully separated from the independant back boiler. You may find several mounting screws that need to be removed and possibly a pipe connection but the two parts of the fire and boiler should seperate.

bisf house chimney flue removal
Remove the fire, back boiler if present, and fireplace surround

bisf house chimney flue removal
Side view of fireplace

bisf house chimney flue removal
Remove Flue Casings

bisf house chimney flue removal
Exposed View

bisf house chimney flue removal
Exposed View

bisf house chimney flue removal
Retention Plate

bisf house chimney flue removal
Loft Support

bisf house chimney flue removal
Pipe Cutter

bisf house chimney flue removal
Cut Pipe

bisf house chimney flue removal
Exposed Flue Liner

bisf house chimney flue removal
Removing Liner

bisf house chimney flue removal
Pipe Cutter In Action

bisf house chimney flue removal
Clean Cut

bisf house chimney flue removal
Cutting Flue In Sections

bisf house chimney flue removal
Another Cut

bisf house chimney flue removal
Flue Casing

bisf house chimney flue removal
Flue Frame

bisf house chimney flue removal
Side View Steel Flue Frame

bisf house chimney flue removal
Fireplace Connection Flange

bisf house chimney flue removal
Box Frame Studwork

bisf house chimney flue removal
Fully Removed

Flue Removal Process

Additional Steps at bottom of post.

First, completely remove the existing fireplace surround. The surround is usually constructed from large slabs which should be pretty easy to break up using a lump hammer or similar. It would be wise to dismantle the top mantle slab first. One stripped away you should be left with the concrete firebox surround. (Images 1 & 2) and also the boxing from around flue in the front bedroom.  ( Images 3 & 4) Note the flared joint located 2 thirds up in the bedroom. (Image 5)

Firstly remove the fire place surround

Side view of fireplace

First, remove the fire place surround (Images 1 & 2) and also the boxing from around flue in the front bedroom.  ( Images 3 & 4) Note the flared joint located 2 thirds up in the bedroom. (Image 5)

Remove Flue Casings

Exposed View

Exposed View

 Starting in the attic the below image shows the cast iron flue tube passing through the ceiling plate as it starts its journey down through the house via the first floor ceiling (Image 6)

Retention Plate

The next image shows the flue at the point where it exits the roof toward the chimney. You can see at this point that it is clamped into place by a surrounding bracket. (Image 7)

Loft Support

As I won't be disturbing the top part of the flue, my first cut will be just under this top clamp, The chain cutter is feed around the tube and locked into position then slid up to the first cut. (Image 8)

Pipe Cutter

The cutter works on a ratchet system which slowly tightens the chain until it cracks the tube, it's quite noisy and a bit scary. Also a note as there was a gas back boiler and fire a liner has been fed through the tube as this needs to be removed first I made 2 cuts. (Image 9)

Cut Pipe

Then using a reciprocating saw through the small gap I cut through the liner then removed the small flue section before removing the liner by pulling down and out from the lounge fireplace. I found this the dirtiest job so be warned lots of soot rust etc. came down with the liner. (Images 10 & 11)

Exposed Flue Liner

Removing Liner

A manageable flue section was cut lower down near the ceiling plate. (Images 12 & 13)

Pipe Cutter In Action

Clean Cut

*CAUTION* if you cut off a flue section which is unsupported the top cut section jumps upwards due to the force of the cut, BE PREPARED.

My next cut was in the bedroom tight to the ceiling pic 1 then half way above floor level Pic 2 then at floor level pic 3. You could cut larger sections but I opted to keep small sections. (Images 14, 15 &16)

Cutting Flue In Sections

Another Cut

Casing

One more cut in the lounge third of the way from the ceiling the cut section being removed from above. The last section which sits in a plate on top of the fire box you can wriggle until its lose and tilt back to lift out. (Image 17)

Flue Frame

You are now left with the frame which is bolted together in 4 sections then another 4 sections in the bedroom bolted to the downstairs frame. (Images 18 & 19)

Side View Flue Frame

Top Of Fireplace

There are wooden batons nailed in the corner angles to which the plasterboard was nailed too, you can pull the nails out to remove the baton to enable to access the frame bolts. This is straight forward but a fiddly job. The bottom of the frame is cast into the concrete plinth I cut the frame at floor level to enable me to remove it as won't be taking up the concrete plinth just yet. Once all the frame has been removed the concrete fire box can be removed in sections although a little heavy easily removed. (Image 20)

Studwork

Then making good the ceilings and floors is the last job but as I'm about to undertake a major refurbishment of the lounge the making good will be part of that project. (Image 21)

Fully Removed

My local scrap merchant took all the scrap away at no cost to me he even loaded it himself!

Hope this is helpful any questions just ask
Doug

Admin Update - Additional Flue removal process images

bisf house flue and fireplace removal images
View of boxed in flue before removal.

bisf house flue and fireplace removal images
Flue pipe in-situ with support cage removed

bisf house flue and fireplace removal images
The upper section of the flue pipe has been cut away and removed

bisf house flue and fireplace removal images
Partial removal of flue cage

bisf house flue and fireplace removal images
View of cut Flue from bedroom

bisf house flue and fireplace removal images
View looking down from 1st floor

bisf house flue and fireplace removal images
Dismantling of fireplace. Gas connections must be removed by a Corgi registered engineer

bisf house flue and fireplace removal images
Original connections disconnected

View of mid floor support bracket

bisf house flue and fireplace removal images
View of fireplace and flue support frame

bisf house flue and fireplace removal images
Removal of hearth

bisf house flue and fireplace removal images
Removal complete

 
Posted : 8 August 2012 12:09 AM
race and race reacted
(@rubyhollebon)
Posts: 10
Member
 

I'm about to start similar work on my property.  I've got down to the timber casing but I'm not planning to go any further whilst the gas fire is still plumbed in and working. Once it's removed I'll start this work in the living room this year, and upstairs in 5 or so years when we replace/move the gas boiler. 

 

My question; is there anything structural to the house with the chimney stack to be wary of or can I make the living room wall flush after removing the flue and stud work?

 

 

 
Posted : 28 May 2022 11:23 AM
(@rubyhollebon)
Posts: 10
Member
 

I'm about to start similar work on my property.  I've got down to the timber casing but I'm not planning to go any further whilst the gas fire is still plumbed in and working. Once it's removed I'll start this work in the living room this year, and upstairs in 5 or so years when we replace/move the gas boiler. 

 

My question; is there anything structural to the house with the chimney stack to be wary of or can I make the living room wall flush after removing the flue and stud work?

 

 
Posted : 28 May 2022 11:24 AM
(@rubyhollebon)
Posts: 10
Member
 

I'm about to start similar work on my property.  I've got down to the timber casing but I'm not planning to go any further whilst the gas fire is still plumbed in and working. Once it's removed I'll start this work in the living room this year, and upstairs in 5 or so years when we replace/move the gas boiler. 

 

My question; is there anything structural to the house with the chimney stack to be wary of or can I make the living room wall flush after removing the flue and stud work?

 

 
Posted : 28 May 2022 11:24 AM
(@rubyhollebon)
Posts: 10
Member
 

I'm about to start similar work on my property.  I've got down to the timber casing but I'm not planning to go any further whilst the gas fire is still plumbed in and working. Once it's removed I'll start this work in the living room this year, and upstairs in 5 or so years when we replace/move the gas boiler. 

 

My question; is there anything structural to the house with the chimney stack to be wary of or can I make the living room wall flush after removing the flue and stud work?

 

 
Posted : 28 May 2022 11:24 AM
(@Trish)
Posts: 12
 

Fantastic post Doug, thank you for sharing this with everyone.

I have been dying to get my old flue and fireplace removed but hadn't a clue how to do it and hubby kept saying it's too difficult! Lol You've just proved him wrong hahaha

It does look pretty easy for the average diy'er did you face any problems or obstacles?

Trish

 
Posted : 21 November 2022 12:03 PM
 Doug
(@datplum108)
Posts: 29
Member
 

Hi Trish
No real problems as such I found cutting and removing the tube quite simple and took about half a day. The frame surrounding it is a little tricky as some of the nuts and bolts on one side joining the frame together are difficult to access due to the stud wall placed up against it, I had taken pictures of this but sadly I had a corrupted memory card so unable to retrieve them.
Have uploaded a couple more the first one is in the bedroom with tube removed but with the clamp and frame in stiu

The second is the tube in stiu you can clearly see the wooden batons that sit in the angle frames which are nailed in place through a hole in the steel these need to be removed to access the frame bolts,The right hand one is tricky to remove as the plaster board is nailed to it

But a competent DIY’er should have no trouble. If you require any further information let me know
Regards
Doug

 
Posted : 21 November 2022 12:03 PM
 Ed
(@Ed)
Posts: 472
 

Fascinating post Doug even though I have no plans to remove mine, which is in use by the boiler. I am looking into whether it's possible to remove the ugly mismatched pink tile fireplace and gas fire that have been stuck onto the front of the firebox.

 
Posted : 21 November 2022 12:03 PM
 Doug
(@datplum108)
Posts: 29
Member
 

Hi Ed
As you say that the flue is in use I’m Guessing you have a back boiler fitted Baxi? if this is the case the gas fire is part of the boiler and you have a very limited and expensive choice of fire fronts, If still available. As for the tiled surround you can do what you like providing you keep the existing dimensions e.g. Depth /size of opening. But don’t forget that you would need to consult a Gas Safe engineer before you start any work when a open flue gas boiler / fire are concerned due to ventilation requirements. if you could post a picture should be able to give you some advice.
Regards
Doug

 
Posted : 21 November 2022 12:03 PM
 Ed
(@Ed)
Posts: 472
 

Hi Doug, we do indeed have a Baxi back boiler for the hot water and central heating, model Bermuda SL3. I was thinking of replacing it either with a combi boiler elsewhere (problem is nowhere obvious to put it) or a modern Baxi Bermuda condensing back boiler in the same place. However, after using relatively little gas last winter I shelved that idea as I thought it would take a long time to recoup the money through increased boiler efficiency.

I was hoping to be able to remove the gas fire unit and fireplace and replace them with a more stylish fire surround/non operational fireplace and leave the back boiler as it is. I suspect though that the fire and boiler might have to be together to work.

The fireplace is large and takes up quite a bit of room but I can live with that, but the way the gas fire has been stuck on the front sticking out even further into the room looks ugly I think.

 
Posted : 21 November 2022 12:03 PM
 Doug
(@datplum108)
Posts: 29
Member
 

Hi Ed
You are correct in thinking that the fire and boiler are connected and you can’t remove the fire to replace with another type. Baxi used to do a selection of different forefronts but were hugely expensive. Even if you went down the new back boiler route the flue liner will need to be replaced at a cost and they only have an electric fire on front although there is talk of a gas one in the pipeline. Most boilers fitted into BISF houses are installed into the old cylinder cupboard and flue through the roof, I’ve fitted them into kitchens and also in the old side shed
Regards
Doug

 
Posted : 21 November 2022 12:03 PM